Chaussée de Bruxelles 178 · 1410 Waterloo · 2025
Kitchen, Waterloo.
An 11 m² closed kitchen at Chaussée de Bruxelles 178 in Waterloo. We opened the load-bearing wall (steel beam, calculated lintel), moved the soil stack 1.80 m, pulled a secondary board and prepared supplies for an island. The kitchen fitter delivered on Tuesday; electrics and plumbing were already in. Six weeks through to the worktop joints.



Opening, wastes, island, stone.
- Address
- Chaussée de Bruxelles 178, 1410 Waterloo
- Year
- 2025
- Duration
- 6 weeks
- Room
- Kitchen
How this job ran.
The same four steps as every job.
Visit
We measure the existing room, the drains, the ceiling height.
Plan
Opening to the living room, soil stack moved, electrics, wastes, island, stone worktop. Kitchen fitter on Tuesday of week 5.
Site
Strip-out, then fitting. One WhatsApp number while the crew is there.
Handover
We walk the joints and the light. Both photos stay in the file.
Works carried out.
Opening to the living room, soil stack moved, electrics, wastes, island, stone worktop. Kitchen fitter on Tuesday of week 5.
- Opening in the load-bearing wall, steel beam, lintel, plaster make-good.nSoil stack moved 1.80 m, fall checked.nSecondary 12-module board, island sockets, oven, hob, hood.nHot/cold supplies; gas capped, induction hob.nScreed and large-format tile, skirting.nKitchen fitter coordination: delivery week 5, ironmongery adjustments.nStone worktop, food-safe silicone joints.



New house, Wavre
Avenue Pasteur 41, 1300 Wavre
Excavation, slab, reinforcement, Porotherm masonry, props, scaffold. Structure underway.
See the job

Façade and roof, Uccle
Rue Vanderkindere 214, 1180 Uccle
External wall insulation, mineral render, aluminium windows, zinc rainwater goods, roof. The family stayed in the house.
See the job

All jobs
Open the list.
See the list